Project Schedule



WRA Phase 27 Interceptor schedule

   -Segment 1 - WRF to UP RR -  January 1, 2017 through July 1, 2018

   -Segment 2 -UP RR to E 26th & Logan - March 1, 2017 through July 1, 2018.  

   -Segment 3 - E 26th and Logan to E E 22nd and Ankeny - Construction March 2018 through July                     2019.

   -Segment 4 - E 22nd and Ankeny to Wayne and Cleveland - Construction April 1, 2017 through                       June 1, 2019

   -Segment 5 - Wayne and Cleveland to E 9th and Jefferson - Construction March 2018 through                         November 2019

   -Segment 6&7 - E 9th and Jefferson to Prospect Park - Construction January 2018 through July                         2019.

   -Segment 8 - Construction of Pump Station at Prospect Park - January 2018 through July 2019.

Click Here for a map of the overall project with segment designations and schedule 