Project Schedule



WRA Phase 27 Interceptor schedule

   -Segment 1 - Wastewater Reclamation Facility to Union Pacific Railroad.  All work on this project has been      completed except for section along Vandalia Road extending from the Wastewater Reclamation Facility at      SE 30th and Vandalia extending 600 feet to the East along Vandalia Road.  This remaining work will be          completed April 1, 2018 through July 31, 2018.  PLEASE NOTE THAT VANDALIA ROAD WILL BE                  CLOSED AT SE 30TH STREET DURING THIS PERIOD.  Click here for Vandalia Road closure details.

   -Segment 2 -UP RR to E 26th & Logan - All work has been completed except for two sections.  The first          remaining section is along Dean Avenue between East 26th and East 27th Street.  The second section is        along East 26th Street between Dean Avenue and Logan Avenue.  This remaining work will be completed      April 1, 2018 through July 31, 2018.  PLEASE NOTE THAT DEAN AVENUE WILL BE CLOSED                      BETWEEN SE 26TH AND SE 27TH DURING THIS PERIOD.  

   -Segment 3 - E 26th and Logan to E E 22nd and Ankeny - Construction June 2018 through July                        2019.

   -Segment 4 - E 22nd and Ankeny to Wayne and Cleveland - Construction April 1, 2017 through                       June 1, 2019.  Work along East 22nd Street has been completed on this segment.  PLEASE NOTE THAT      THE OUTSIDE SOUTHBOUND TURN LANE OF HUBBELL AVENUE WILL BE CLOSED DURING THIS        PERIOD.  

   -Segment 5 - Wayne and Cleveland to E 9th and Jefferson - Construction March 2018 through                         November 2019.  Residential Streets will be closed along the project alignment as construction                        progresses.    

   -Segment 6&7 - E 9th and Jefferson to Prospect Park - Construction June 2018 through October                      2019.

   -Segment 8 - Construction of Pump Station at Prospect Park - June 2018 through December 2019.

Click Here for a map of the overall project with segment designations and schedule 